swindon-interiors-project-vantage

Project Description

Client:   Cineworld
Location:  Project Vantage
Completed:   November 2016

Swindon Interiors were pleased to be announced as the Principal Contractor for Cineworld’s new concept HQ in London.

This was following on from many successful cinema projects with Cineworld, along with G&W Contracting as the design and build contractor for the M&E side of the project.

Project Brief – To develop & deliver the vision into reality

To deliver a complete concept, from a blue-chip client’s vision of unusual & exciting offices, into the reality of a vibrant and comfortable workspace –

Project Overview – To create 2 floors of working offices out of approx. 17,900 square feet of open plan office space.

Project Rundown:

As principal contractor for the fit out;

  • To plan, organise and mobilise approx. 15 different trades for this lucrative fit out project.
  • Liaising directly with the client, architect, interior designer, landlord & facilities management company.
  • Meeting the client’s deadline for relocating to these newly refurbished, highly visible offices, in the west of London.

Example of trades Involved: M&E (design & build), ceilings & partitions, carpenters & joiners, flooring, painters, tiling, cubicles, fire walls, data installations, graphics, blinds. Many of these trades as bespoke services and suppliers, specifically tailored to client’s design requirements.

G&W were involved with the design & build of all M&E services for lighting, emergency lighting, alarm & security systems & data (including server rooms).

The project encompassed work over 2 floors, running to a 12 week programme and was to implement services for new, concept offices, to a former, open plan environment. The results are fantastic and Swindon Interiors/G&W were pleased to be a part of it.